There’s been some heavy lifting going on Benalla Station in recent weeks.
As part of the ongoing Inland Rail project, a 750-tonne mobile crane was used to lift in three more 34-tonne pre-cast concrete crown units (known as culverts) that will eventually form the new pedestrian underpass underneath the rail corridor and connect station platforms.
The crown units are 3.5m high and 6.1m wide.